72nd Place Lifeguard Station Repairs
Additional project updates and information will be published on an on-going basis.
Background
The 72nd Place Lifeguard Station Repairs Project was completed in May 2025 and replaced the exterior building stairs and perimeter fence as they were at the end of their useful life. The project addressed damage and deterioration due to age and corrosion of materials in a harsh marine climate. The improvements now provide safe access to the viewing platforms for life safety staff to monitor surrounding activities and respond promptly to beach users.
Timeline
Design | Fall 2024 |
Bid | February 2025 |
Construction Start | February 2025 |
Construction Ends | May 2025 |
Project timeline is set barring weather delays and other unforeseen circumstances.
Objectives
- Improve public safety
- Improve infrastructure quality
- Extend usability and useful life of facility
Proposed Features
- Replace exterior building stairs and perimeter fence
- Address damage and deterioration of building facilities
Project Funding
The 72nd Place Lifeguard Station Repairs Project is funded by the Tidelands Fund.